Flag of Vietnam

Remediation Status and Schedule

Language: English | Vietnamese

An estimated 73,000 cubic meters of soil and lake sediment at Danang Airport will be treated in two phases.

Read more about the areas being remediated
Read more about the remediation process

Project Schedule

The project schedule is subject to change.

2012

  • August 9: Project launch ceremony.
  • September through December (rainy season): Limited fieldwork.

2013

  • Construction of structure to hold contaminated soil for treatment.
  • Excavation (Phase 1):
    • Storage area;
    • Mixing and loading area;
    • Southern end of drainage ditch;
    • South end of eastern wetland; and
    • Pacer Ivy storage area.
  • Installation of treatment system (Phase 1).
  • September through December (rainy season): Limited fieldwork.

2014

  • Phase 1 treatment.
  • Sampling of soil treated in Phase 1 to confirm treatment effectiveness.
  • Phase 1 treated soil transferred from treatment structure.
  • September through December (rainy season): Limited fieldwork.

2015

  • Excavation (Phase 2) and dewatering of lake sediment:
    • Sen Lake;
    • Northern end of drainage ditch;
    • Northern end of eastern wetland; and
    • Area between eastern wetland and drainage ditch.
  • Installation of treatment system (Phase 2).
  • September through December (rainy season): Limited fieldwork.

2016

  • Phase 2 treatment.
  • Sampling of soil treated in Phase 2 to confirm treatment effectiveness.
  • Phase 2 treated soil from transferred from treatment structure.
  • Site restoration.

See also: